Project Overview
Margaret Todd Senior Center and Downtown Recreation Center/Novato Gymnastics Center Roof Replacement (CIP #19-006 & 24-004).
Description
As of 2024, the roofs at the Margaret Todd Senior Center and the Downtown Recreation Center had aged and weathered to a state where leaks were allowing potential damage to the roof structure, and resulting in disruption of the activities in both buildings. City staff had been addressing isolated issues for several years, and proposed the addition of a waterproof barrier to revitalize both roofs.
Removing existing roofs and installing entirely new roofs was not a cost efficient option, and would be extremely disruptive to the community as many activities would be suspended for a significant length of time. Staff realized that much of the existing roof was in acceptable condition, and some portions needed repairs. Staff worked with consulting architects to inspect and analyze the roofs, make needed dryrot repairs, and identify a Duro-Last PVC membrane system that could be installed on both roofs to provide a new surface barrier to water and wind damage. The system carries a fifteen year warranty and is supported by the manufacturer.
In May and June 2025, following dry rot repairs and inspection of the roof structure, the new roof overlays were installed at the Downtown Recreation Center and the Margaret Todd Senior Center. Public Works staff and inspectors from Duro-Last inspected the installation, which was completed by a Duro-Last certified contractor. The community’s patience and consideration during effected programing and parking was appreciated by the City staff. The City is excited to have the overlays on both buildings as they will provide protection against weather and provide a better experience for the community.
Location
950 7th Street, Novato Gymnastics Center / Downtown Recreation Center
1560 Hill Rd, Margaret Todd Senior Center
Benefit
Life and Safety and Building Maintenance.
Schedule
Project was completed between May and June 2025.
Cost
Engineer’s Estimate: $1,322,000
Construction Contract Award: $1,110,030
Final Construction Contract Cost: $950,970.
Bid Documents
Connect With Us
Sign up to receive email updates for this project. Note: select both Calendar and News categories to be notified of upcoming meeting and project updates.
Project Managers
City Contact
Miguel Carrillo
415-827-3950
Site Superintendents
MTSC
Carlos Avelar
510-513-3838
DRC/Gymnastics Center
Jose Ochoa
510-427-9368