MTSC and DRC/Novato Gym Roof Replacement

 Gymnastics Center

Project Overview

Margaret Todd Senior Center and Downtown Recreation Center/Novato Gymnastics Center Roof Replacement (CIP #19-006 & 24-004).

Description

As of 2024, the roofs at the Margaret Todd Senior Center and the Downtown Recreation Center had aged and weathered to a state where leaks were allowing potential damage to the roof structure, and resulting in disruption of the activities in both buildings.  City staff had been addressing isolated issues for several years, and proposed the addition of a waterproof barrier to revitalize both roofs. 

Removing existing roofs and installing entirely new roofs was not a cost efficient option, and would be extremely disruptive to the community as many activities would be suspended for a significant length of time.   Staff realized that much of the existing roof was in acceptable condition, and some portions needed repairs.  Staff worked with consulting architects to inspect and analyze the roofs, make needed dryrot repairs, and identify a Duro-Last PVC membrane system that could be installed on both roofs to provide a new surface barrier to water and wind damage.  The system carries a fifteen year warranty and is supported by the manufacturer.

In May and June 2025, following dry rot repairs and inspection of the roof structure, the new roof overlays were installed at the Downtown Recreation Center and the Margaret Todd Senior Center.  Public Works staff and inspectors from Duro-Last inspected the installation, which was completed by a Duro-Last certified contractor.  The community’s patience and consideration during effected programing and parking was appreciated by the City staff.  The City is excited to have the overlays on both buildings as they will provide protection against weather and provide a better experience for the community.

Location

950 7th Street, Novato Gymnastics Center / Downtown Recreation Center

1560 Hill Rd, Margaret Todd Senior Center

Benefit

Life and Safety and Building Maintenance. 

Schedule

Project was completed between May and June 2025.

Cost

Engineer’s Estimate: $1,322,000

Construction Contract Award: $1,110,030

Final Construction Contract Cost: $950,970.

Bid Documents

Notice To Contractors

Notice of Intent

Bid Abstract

 

Project Updates
Project-related Information
Community Workshops & Meetings

Connect With Us

Sign up to receive email updates for this project. Note: select both Calendar and News categories to be notified of upcoming meeting and project updates. 

Project Managers

City Contact
Miguel Carrillo
415-827-3950

Site Superintendents 

MTSC
Carlos Avelar
510-513-3838

DRC/Gymnastics Center
Jose Ochoa
510-427-9368